How were the sites for the three year rollout chosen?

Posted on Thursday 29 March 2012 by Dan Warne

Today NBN Co announced that the NBN fibre rollout plan will expand to around a third of the country’s homes and businesses over the next three years, across 1,500 communities in every state and territory, covering 3.5 million premises.

An interesting story behind the story is how these locations were chosen.

A set of logistical, engineering and practical considerations were balanced with the government’s policy objectives to determine the rollout sequence.

All of these factors were built into a mathematical algorithm, and a clever Australian company called Biarri developed the modelling into a software tool that lets us plan the most efficient sequence of areas for the rollout.

Some of the government's policy objectives that were built into the algorithm included:

  • Construction should be across both rural and metropolitan areas
  • Construction should be across all states and territories
  • The rollout in Tasmania should be finished by 2015
  • All new developments with over 100 premises should be covered


NBN Co added the following objectives

  • The fixed wireless broadband rollout should be completed in 2015
  • Satellite broadband via NBN Co’s own satellites should be available by 2015
  • Areas where there are a large number of new developments should have priority, to avoid old technologies being installed, only to be replaced with the National Broadband Network later.


There were a set of practical considerations that factored into the algorithm, too.

While most people understandably focus on when they’ll be getting the NBN in their street, a truly more important consideration is whether there is something to connect their street back to!

We call these “transit links” (high speed cables that connect localities back to NBN Co’s core network). Transit links connect to “points of interconnect” – exchange buildings where internet and telephone providers connect their networks to ours.

NBN Co is working to complete the transit network by 2015 in order to link up all the 121 points of interconnect nationwide. That’s a large body of work going on behind the scenes during the next three years.

The progress in the installation of transit links and points of interconnect contributes to decisions about what are the most viable communities to start construction in next.

Another important design rule in building the fibre network is that where we have started construction in an area, we will complete coverage there before moving on to another area. “Fibre serving areas” are broken up into modules of around 3,000 premises, and after we start construction on one module, we complete all the modules in that area.

If construction work for your area hasn’t been announced as part of our plans for the next three years, rest assured that we’ll be updating our construction plans once a year, outlining the next series of communities in which NBN construction is scheduled to commence.

View more about:
Construction, Biarri, NSW, VIC, TAS, NT, QLD, ACT, SA, WA

By Dan Warne, NBN Co Blog Editor

Dan has been a technology journalist for the last 10 years, first with broadband community site Whirlpool.net.au, and later with APC Magazine and Sydney Morning Herald. He has a baby boy, two chocolate labradors, and a fascination with broadband and everything it can make possible. Email: danwarne@nbnco.com.au

Recent blog posts

  1. CategoryCommunity

    How superfast broadband is enabling better home security

    How superfast broadband is enabling better home security

  2. CategoryCommunity

    Teleworking pays dividends

    Teleworking pays dividends

  3. In the orange

    In the orange

  4. Sydney switches on the National Broadband Network

    Sydney switches on the National Broadband Network

Comments

All comments are moderated and will be reviewed before they are published. To ensure your comments will be published, please read and follow our Community Guidelines.

By commenting you agree to Disqus' (the blog comment platform owner, a US company) Terms of Service and Privacy Policy and to the NBN Co Privacy Policy and NBN Co's Community Guidelines. NBN Co and Disqus may collect, store and use personal information that you post in accordance with these terms and policies.

NBN Co Logo

Blog Community Guidelines

NBN Co welcomes your comments. We are committed to ensuring that issues discussed on the blog are relevant and expressed calmly and in a way that is respectful of all participants. Your use of the NBN Co Blog is subject to these guidelines and our general website Terms and Conditions of Use.

To ensure the standard of discussion on the site remains polite and on-topic, NBN Co reviews all comments before publication. Comments will be reviewed during normal business hours (9:00 - 5:00 PM, Monday to Friday) and, if accepted, will generally be posted within two hours. You will not be contacted if your comment is not accepted.

You should NOT post any comment that:

  • is aggressive, inflammatory or defamatory;
  • is too long or repeats previous posts;
  • misrepresents NBN Co, its shareholder or its board members;
  • is not about the topic of the discussion;
  • is not relevant to the NBN or broadband;
  • attacks or impersonates individuals;
  • is, in our judgement, mainly about promoting an external website; or
  • presents another legal, commercial or technical risk.

Your comment should be your own, don't copy from someone else.

You must supply a valid email address to be able to post a comment. Your email address will not be published.

We reserve the right to edit, withhold or remove any comment that does not comply. You may be personally liable if your comment is unlawful.

Comments about our moderation policy will not be published. The moderator's decision is final.

If you find a comment offensive, please contact the NBN Blog team and tell us why you think the comment breaches these guidelines. Please include the web address for the page on which the comment appears in your email.

You agree that we can use your comment (in whole or in part) in other forums, including on our website and in marketing materials.

NBN staff and contractor comments

NBN staff and contractors should review the social media policy available on the NBN Intranet before commenting on the site.

Customer Service

NBN Co does not sell directly to the public, so any questions about your specific NBN internet connection should be directed to your telephone or internet service provider.



blog comments powered by Disqus